Key takeaways
- 1The team presents its conclusions, including its recommendation regarding certification.
- 2The certification body requires the client to analyse the cause of each nonconformity and describe the specific correction and corrective actions taken or planned, within a defined time (§9.4.9).
- 3The body reviews the corrections, causes and corrective actions for acceptability, verifies the effectiveness of the actions taken, and records the evidence (§9.4.10).
The closing meeting ends the audit, not the certification. ISO/IEC 17021-1 sets out the steps between the audit team's recommendation and a certificate, each in its own clause, without fixing the order of steps 2 to 4. It sets one time limit. The other timeframes it mentions are agreed at the closing meeting or defined by the certification body.
1. The closing meeting sets the terms
The team presents its conclusions, including its recommendation regarding certification. Nonconformities are presented so that they are understood, and the timeframe for responding is agreed (§9.4.7.1). The client is also told how and when the body reports, the timeframe for a correction and corrective action plan, the body's post-audit activities, and how complaints and appeals are handled (§9.4.7.2).
2. The client analyses causes and responds
The certification body requires the client to analyse the cause of each nonconformity and describe the specific correction and corrective actions taken or planned, within a defined time (§9.4.9). The analysis is the client's own: the auditor refrains from suggesting causes or solutions (§9.4.5.3).
3. The body reviews the response
The body reviews the corrections, causes and corrective actions for acceptability, verifies the effectiveness of the actions taken, and records the evidence (§9.4.10). It tells the client the result, and whether an additional full audit, an additional limited audit or documented evidence, to be confirmed at future audits, will be needed.
4. The audit report
The client receives a written report for each audit. The certification body owns it; the audit team leader is responsible for its content (§9.4.8.1, §9.4.8.2). It exists to enable an informed certification decision. The audit team may identify opportunities for improvement but does not recommend specific solutions.
5. The review and the decision
The minimum information the audit team provides includes the report, its comments on the nonconformities and the client's actions, and its recommendation (§9.5.3.1). Before deciding, the body confirms that the information is sufficient, verifies the correction and corrective actions for any major nonconformity, and accepts the plan for any minor one (§9.5.2).
If the actions on a major nonconformity cannot be verified within 6 months after the last day of stage 2, another stage 2 is conducted before certification is recommended (§9.5.3.2).
The decision is taken by people who did not carry out the audit (§9.5.1.1) and is recorded (§9.5.1.4).
6. The certification documents
The body provides certification documents by any means it chooses (§8.2.1). They identify, among other things, the effective date, which cannot be earlier than the decision; an expiry or recertification due date consistent with the cycle; a unique identification code; the standard with its issue status; and the scope (§8.2.2).
What starts with the decision
The first three-year cycle begins with the certification decision (§9.1.3.2). The first surveillance audit is not more than 12 months from the certification decision date (§9.1.3.3).
CAS — An EGAC accredited MS certification body No. 012418. Accredited scope: ISO 9001, ISO 14001, ISO 45001, ISO 22000, ISO 50001 and ISO 22301. Certificates accredited for ISO 9001, 14001, 45001, 22000 and 50001 fall within EGAC's IAF MLA scope; ISO 22301 is accredited by EGAC and sits outside that scope.